Friday 6 September 2024 9.00am EDT

During the last week Chandra completed the observing schedule as planned.

Chandra passed through the 7th, 8th, and 9th eclipses of the season on Aug 31, Sep 3, and Sep 5 respectively, with nominal power and thermal performance.

Real-time procedures were executed on Sep 4 to perform a routine self-check of the Electrical Interface Assembly (EIA) Sequencer and to perform a diagnostic dump of the Control Processing Electronics (CPE).

The schedule of targets for the next week is shown below and includes observations of Her X-1, which was accepted as a Target of Opportunity on Aug 16.



------------------------------------------
        GAL034.8-00.6IRDC      ACIS-I       Sep  8
        1E2215.7-0404/1E       ACIS-I       Sep  9
        GAL034.8-00.6IRDC      ACIS-I
        1E2215.7-0404/1E       ACIS-I
        70OPH                  HRC-I        Sep 10
        herx-1                 ACIS-S/HETG
        CasA (4 obs)           ACIS-I
        CasA (4 obs)           ACIS-S
        Radiation Belts                     Sep 11
        NGC6204                ACIS-I
        trappist-1             HRC-S
        trappist-1             HRC-S
        herx-1                 ACIS-S/HETG
        PerseusCluster         ACIS-I       Sep 12
        IGRJ18303-3345         ACIS-S
        trappist-1             HRC-S
        trappist-1             HRC-S
        SS433e0                ACIS-I
        trappist-1             HRC-S        Sep 13
        trappist-1             HRC-S
        B31428+422             ACIS-S
        Radiation Belts
        NGC6242                ACIS-I
        G29-38                 HRC-I        Sep 14
        eMACSJ1658.6+1519      ACIS-I
        DESJ2349-5113          ACIS-I
        IGRJ17342-4049         ACIS-S       Sep 15
        SPT-CLJ2233-5552       ACIS-I
        1E2215.7-0404/1E       ACIS-I
        SDSSJ151354.48+1451    ACIS-S
        G29-38                 HRC-I

------------------------------------------

All spacecraft subsystems continued to support nominal operations.